Question 1) During a Sprint, a Development Team determines that it will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected? 
A) The Scrum Master, the project manager and the Development Team.  
B) The Product Owner and the Development Team. 
C) The Product Owner and all stakeholders. 
D) The Development Team. 

Question 2) What is the primary way a Scrum Master keeps a Development Team working at its highest level of productivity? 
A) By facilitating Development Team decisions and removing impediments. 
B) By ensuring the meetings start and end at the proper time. 
C) By preventing changes to the backlogs once the Sprint begins. 
D) By keeping high value features high in the Product Backlog.

Question 3) Which of the following is a responsibility of the Product Owner? 
A) Determine the appropriate release dates. 
B) Determine the Team composition necessary for success. 
C) Determine the appropriate solution or approach for the product. 
D) Determine the length of the Sprints.



Correct Answer
Question 1) : Correct Answer B : Product owner and development team should be present
Question 2) : Correct Answer A : By facilitating Development Team decisions and removing impediments.
Question 3) : Correct Answer A : Product owner is the voice of customer. He determines the scope and also the release dates of the products.